CERTIFICATE COURSE IN CONTRACT ADMINISTRATION (INTAKE 6)

Organised by SISV QS Division

SISV QS Division, together with a team of experienced practitioners and academics in the relevant field, is pleased to conduct a certificate course in Contract Administration.

The course is designed and structured to cover key aspects of contract administration and how these are and should be addressed within the SIA and PSSCOC contractual framework. It will be of relevance to all stakeholders in the development process such as developers, quantity surveyors, managing agents, project managers, superintending officers, architects, engineers, construction managers, contracts managers and executives, contractors and sub-contractors including specialist contractors and suppliers of construction materials and products.

The course comprises 16 lectures which will be conducted at Singapore Institute of Surveyors and Valuers and includes 2 tutorial sessions in preparation for a written examination to be held at the end of the course. A Certificate in Contract Administration will be awarded by SISV to candidates who have attended at least 75% of the course and upon successful completion of the examination .

The 6th intake is scheduled to commence on Monday, 06 July 009 . We welcome applicants who possess either a Diploma in a construction related discipline or have at least 5 years of relevant work experience to register for the course. A copy of the course prospectus and application form is available for download in the weblink on this page. If you require a hard copy of the course prospectus and application form, please contact us at Tel: 65-6222-3030 or Fax : 65-6225-2453 or email judy@sisv.org.sg with your mailing details, or you may collect a copy from our office .

We look forward to welcoming you as a candidate to the course.

[Return to Top]

COURSE OUTLINE

Week 1 -- Roles and duties of architect, superintending officer, quantity surveyor and project manager; contractor’s obligations; administration principles.
Week 2 & 3 Instructions, certificates and notices; commencement and completion; extension of time and liquidated damages.
Week 4 Variations and payments including Security of Payment (SOP) payment protocols.
Week 5 to 7 Defects, indemnities and liabilities; construction insurance, bonds and guarantees;
Week 8

Overview of dispute resolution processes.

     